TIGO Prepaid Upgrade

2010 - 2011

Role: Program/Project Manager + Solution Architect
Employer: Comptel Oyj
Technology/Tools: HP NonStop Servers, HP INS software and CBOSS rtBilling platform Software / Project Management Methodologies and Tools
Executed: August 2010 - August 2011
Link: http://www.tigo.com.co/
References: (CBOSS) Matti Raitmaa or Mojgan Otterstrom and (TIGO): Liliana Ramirez
Note: Image is the property of Tigo

The goal of this project was to perform an upgrade to the TIGO Prepaid platforms to allow TIGO to monetise opportunities while giving them greater for greater capacity and increased performance. At the time of project execution, TIGO had more than 8 million prepay subscribers.

This project was delivered with a team assembled from all relevant departments of CBOSS.

The project was divided into three distinct, but overlapping phases:
  1. Scoping, Statement of Work, Contract and Customer Project Planning

    In addition to the standard Software Product, CBOSS rtBilling, the customer requested some enhancements to the core functionality to allow them to monitor the system in a more efficient manner. This highlighted the need for a development phase to be included in the project. Onsite, together with the customer project and operations teams, I outlined the overall solution and presented the deployment approach Simultaneously, together we created the Statement of Work document which detailed the project deliverables,quality requirements and acceptance criteria. Also, a very clear change control process was agreed Taking the customers, and other key stakeholders, needs into account, the project management plan, resourcing plan (for onsite work) and communications plan were created and baselined. These documents and guides were revisited throughout the project and were key in the success of the project


  2. Internal Software Development Project

    Design, development and test teams chosen from different departments As agreed in the communications plan, the customer project was kept informed of the progress of the development project As agreed in the Statement of Work and Test Plan, actual customer data was used as the basis for the testing effort. This made regular reporting easier and more relative. Also the value of the test results was substantially greater than if a set of data had been generated for testing purposes. The software and accompanying documentation were delivered as outlined in the Statement of Work


  3. Customer Delivery Project

    Delivery was performed onsite in Colombia by a virtual team of CBOSS specialists. A travel plan was made and budget agreed with the customer as per Statement of Work Number of man days onsite exceeded 300 During the Delivery Project, Customer Training was delivered onsite by the project team as per Statement of Work


Project Challenges

Project Result

The project delivery was completed one day ahead of schedule and under budget. The project received a 4.5 of 5 rating from the customer. Very successful overall.

My Roles: Program/Project Manager + Solution Architect

Apart from executive account management, this was an all emcompassing role. This was a stategic delivery towards this customer amid tight competition both external and internal within the customers international organisations.

  • Project Scoping/Planning/Budgeting
  • Customer Relationship/Expectation Management
  • Project Reporting to both the Customer and the Internal Steering Board
  • Collaboration with other vendors